Wolf River Estates

Client Name

Delmas Development Inc.

Project Type

homesite clearing, dam and pond installation construction project

Wolf River Estates

Problems

This project consisted of land clearing, excavation, and utility prep for homesites on a 40-acre development. VKM completed the excavation, earthmoving, hauling, and shaping necessary to build a 250-foot-long, 7-foot-high earthen dam to create a recreational 7.5-acre lake.

Key project elements:

  • Construction of an emergency spillway, core trench, and lake drain
  • 12-inch gate valve and concrete drain pipe spillway
  • Over 25,000 CY of earth and spoil moved
  • Stream repair over 1000 feet using stone and gravel to manage flow and erosion

alt text alt text alt text

Solutions

A comprehensive strategy of heavy civil works including:

  • Erosion and sediment control implementation
  • Hydrologic modeling for dam sizing and outlet structure design
  • Dewatering plan with well points and temporary diversion channels
  • Engineered backfill placement and compaction monitoring

Result

This project is similar to Greenbrier Dam, involving lake and dam construction, dewatering (well points), excavation, spoil removal, and compaction.